Installation 22
4) The unit needs to be protected before hoisting. Pad some thick EPE or other things between the sling and the frame of
the unit.
After completing the above steps, start hoisting.
During the hoisting process, it is necessary to ensure that the force in all directions is consistent and the unit is stable.
It is necessary to protect the aluminum frame with some paper or wood.
After the hoisting is completed, connect the upper cabinets, lower cabinets, and cabinet parts, as shown in the Figure 2-17
below.
Figure 2-17 Aluminum profile and foaming board