7 CHECKLIST FOR COMPLETED INSTALLATION
7.1 Moving and Placing Equipment
1. Unpack and check received material.
2. Proper clearance for service access has beenmaintained around the equipment.
3. Equipment is level and mounting fasteners are tight.
4. If equipment has been disassembled for installation, unit must be reassembled per instructions.
7.2 Electrical Installation Checks
1. Supply voltage and phase matches equipment nameplate.
2. Power wiring connections completed to the disconnect switch and unit.
3. Power line circuit breakers or fuses have proper ratings for equipment installed.
4. Control wiring connections completed betweenindoor evaporator and heat-rejectionequipment.
5. All internal and external high- and low-voltage wiring connections are tight.
6. Confirm that unit is properly grounded to anearthground.
7. Control transformer setting matches incoming power.
8. Electrical service conforms tonational and local codes.
9. Check blowers and compressors for proper rotation.
7.3 Piping Installation Checks
1. Piping completed tocoolant loop.
2. Piping has been leak-checked.
3. Piping has beenflushed toclear debris, pipe dope, and contaminants.
4. Piping is properly sized, sloped and trapped as showninthe piping schematics.
5. Check piping inside and outside of equipment for proper support and adequate spacing to prevent rub-
through.
6. Ensure that factory clamps have been reinstalled.
7. Drainline connected, not obstructed, and pitched per local code.
8. Water supply line connected to humidifier and not leaking.
9. Condensate drain connected.
10. Condensate pump, if applicable, is operational.
7.4 Other Installation Checks
1. Ducting or plenum assembly complete (if required), maintain access to filters.
2. Filters installed.
3. Check fasteners that secure , reheats, humidifier and motorssome may have become loose during shipment.
4. Verify water detectionis properly installed around all units (recommended).
5. Blower drive system rotates freely and belts are properly aligned and tensioned.
6. All fans are free of debris.
7. Remove rubber band from float in optional infrared humidifier.
7 Checklist for Completed Installation
73

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Vertiv Liebert CW Series and is the answer not in the manual?

Vertiv Liebert CW Series Specifications

General IconGeneral
BrandVertiv
ModelLiebert CW Series
CategoryUPS
LanguageEnglish

Related product manuals