1.4 Filling Loop
On all models, set the pressure to 1.0 bar when cold.
Special attention must be given to corrosion inhibitor concentrations where there
is a need to top up the system. See Section 1.5.
It is recommended to isolate all electricity supplies to the appliance before topping
up system pressure.
System Boilers – The filling loop is located above the expansion vessel.
Remove the dust caps, then fit the flexible hose (1) at both ends, open the valves
to increase system pressure.
Your installer will be able to advise the
position of the filling valve.
After topping up the system the valve(s)
must be fully closed and the flexible hose
disconnected from the valve(s), and dust
caps refitted.
Expect a small water loss from the hose.
Combination Boilers – The filling loop is
accessed by opening (1) and removing (2)
the access cover.
Remove the dust caps, then fit the flexible
hose (3) at both ends, open the valves (4) to
increase system pressure.
After topping up the system the valve(s)
must be fully closed and the flexible hose
disconnected from the valve(s), and dust
caps refitted.
Expect a small water loss from the hose.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the WarmFlow Agentis Series and is the answer not in the manual?

WarmFlow Agentis Series Specifications

General IconGeneral
Installation TypeWall-mounted
TypeCondensing
Dimensions700 x 400 x 300 mm
EfficiencyUp to 93%
ControlDigital
Heating CapacityVaries by model
Warranty5 years

Related product manuals