ControlMaster CM30, CM50 and CMF310
Universal process controllers,
1
/4,
1
/2 DIN and fieldmount 7 Advanced Level
82 IM/CM/ED–EN Rev. X
…Functions / …Bank Control
…Bank Control Using First In First Out (FIFO) and Rotate modes on a 3 pump system
Bank Size Select the number of stages (pumps) required for the application from 2 to 6 or Off.
Off disables the Bank Control functionality.
Control Source Select the analog signal to act as the control signal for the bank control.
This is normally the Process Variable (PV) for most pump control applications.
Stage 1 (6)
Off Trip
Select the Control Source value (PV) at which the output (pump) is turned off.
On Trip
Select the Control Source value (PV) at which the output (pump) is turned on.
Output
Select the initial output (relay or digital output) that the output is assigned to by
default (for example, when FIFO or Rotate mode is not in operation).
Schedule
Select the wear levelling schedule required:
Off – the output is not controlled by the bank schedule.
The state of the output is controlled entirely by its associated trip points.
FIFO – the output is controlled according to the FIFO schedule mode.
Rotatethe output is controlled according to the Rotate schedule mode.










P1
P2
P3
4 m
3 m
2 m
1 m
First In First Out (FIFO)
Level P1P2P3 LevelP1P2P3
Seq. 1 1.3 m Seq. 6 2.2 m
Seq. 2 2.2 m Seq. 7 0.8 m
Seq. 3 3.6 m Seq. 8 1.8 m
Seq. 4 4.3 m Seq. 9 0.8 m
Seq. 5 2.8 m Seq. 10 1.8 m
Rotate Pump Cycling
Level P1 P2 P3 Level P1 P2 P3
Seq. 1 1.3 m Seq. 6 2.2 m
Seq. 2 2.2 m Seq. 7 0.8 m
Seq. 3 3.6 m Seq. 8 1.8 m
Seq. 4 4.3 m Seq. 9 0.8 m
Seq. 5 2.8 m Seq. 10 1.8 m
On trip
at 4 m
Off trip
at 3 m
On trip at 1.5 m
Off trip at 1 m
Pump 2
Pump 3
Pump 1
On trip
at 3.5 m
Off trip
at 2.5 m

Table of Contents