PCS100 AVC-20 User Manual 45
7 OPERATING THE PCS100 AVC-20
7.1 Starting and Stopping the PCS100 AVC-20
The primary method of starting and stopping the PCS100 AVC-20 is via the Graphical Display Module (GDM) which
is mounted in the door of the Master Controller Enclosure. This is deemed Local Control. Start/Stop control of the
PCS100 AVC-20 via the digital I/O terminals (Section 11.2. Control Connections) is deemed Remote Control.
7.1.1 GDM Control
The Start (I) / Stop (O) /Reset button in the Navigation & Control Panel allows GDM control of the PCS100 AVC-20.
When the PCS100 AVC-20 is stopped (Bypass) a green Start (I) button will show, and when running (RUN) a red
Stop ( ) button will show. Pressing the Start (I)/ Stop ( )/ Reset button followed by YES in the following
confirmation screen will cause that action to be taken. Figure 7-1: GDM Status Page shows the status page when
the PCS100 AVC-20 is running.
Figure 7-1: GDM Status Page
Note: If parameter A31 GDM Control Enable is set to False the Start/Stop/Reset button will not be
displayed.
Start/Stop/Reset