58 PCS100 AVC-20 User Manual
This parameter adjusts the recording threshold for sag events recorded in the
Event Log and on the Summary Page. It does not alter the operation of the PCS100
AVC-20.
Power quality meter surge recording threshold.
Percentage of parameter 13 Supply Voltage
This parameter adjusts the recording threshold for surge events recorded in the
Event Log and on the Summary Page. It does not alter the operation of the PCS100
AVC-20.
Table 8-3: Menu 1 System Electrical Parameters
8.3.4 Menu 2 Commissioning
The menu contains parameters for commissioning and testing
Note: This menu is only visible with Tech login
Provides a check of the phasing of the supply cables.
When this parameter is set to True the output regulation voltages will be V1-100%, V2-
105% and V3-110% of the parameter 13 Supply Voltage setting.
This check should be performed during commissioning. See section 2UCD280000E004
PCS100 AVC-20 Commissioning Checklist.
Selects output voltage under Test Mode.
PU. Base = 13 Supply Voltage
Selects output frequency under Test Mode.
Nameplate rating of PCS100 AVC-20