IEC13000060-1-en.vsd
IEC13000060 V1 EN-US
Figure 6: Select the TCP/IPv4 protocol and open Properties
5. Select Use the following IP address and define IP address and Subnet mask if the front port is
used and if the IP address is not set to be obtained automatically by the IED,see
Figure 7. The IP
address must be different from the IP address chosen for the IED.
IEC13000062-1-en.vsd
IEC13000062 V1 EN-US
Figure 7: Select: Use the following IP address
6. Use the ping command to verify connectivity with the IED.
7. Close all open windows and start PCM600.
1MRK 504 165-UUS Rev. J Section 4
Starting up
Transformer protection RET670 51
Commissioning manual
© 2017 - 2021 Hitachi Power Grids. All rights reserved