Mast, 2 Stage
PS S7.0 7110
F-code Section C-code
Version no T-code
001 OE35
265
Service Manual 1996-10-15
© BT Products
2.2. Installation
1. Install mast on unit using four mast mounting bolts
secure mast in place. Torque mounting bolts to 200
ft-lb. (271 N•m).
2. Connect hydraulic hose to lift cylinder.
3. Hydraulically lift inner column enough to get
platform in.
4. Hoist platform and slide up inner column.
5. Connect lift chain anchor pins.
6. Connect steering wheel chain and electrical cable
to unit.
7. Loosen locking nuts on chain anchors. Adjust nuts
until both chains are free of twists and of equal
tension. Tension is correct if you can force lift chain
sideways approximately 1/2 in. to 1 in. before
platform raises slightly.
8. Retighten locknuts on chain anchors.
9. Grease all chain sheaves.
10.Bleed air from cylinder.
11.Install and connect battery and test operation of
mast and unit.