Clearance required between the front of the
chassis and the inside of the cabinet (if used) or
the edge of the cold aisle (if no cabinet) for the
cable management frames and the optional front
doors
16Air intake from cold aisle for the supervisor and
I/O modules
7
Front service clearance required for installing
the chassis and replacing the modules
17Air exhaust to hot aisle for all modules and
power supplies
8
No left side clearance required (no airflow on
left side)
9
Figure 133: Clearances Required for the Cisco Nexus 7004 in a Two-Post Rack with Front-Mount Brackets
No left side clearance required (no airflow on
left side)
8Cisco Nexus 7004 chassis1
Chassis width.9Cable management frames2
Cisco Nexus 7000 Series Hardware Installation and Reference Guide
189
Technical Specifications
Cisco Nexus 7004 Chassis Clearances