2.4 -
Starter Operation Limits
Starter operation sequence is limited as follows:
-
Automatically by the F
ADEC to 80 seconds.
-
For manual dry motoring to 30 seconds.
NOTE
On start, the F
ADEC automatically performs a dry motoring after an aborted
start (commanded by the FADEC or by pilot action). The FADEC limits the use
of starter to a total duration of 80 seconds, including dry motoring and start
sequences.
Should several start-up sequences be necessary, respect the following spacings
between attempts:
- Between 1st and 2nd sequence: wait for 1 minute.
- Between 2nd and 3rd sequence: wait for 5 minutes.
- Between 3rd and 4th sequence: wait for 30 minutes.