Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0 19
Figure 9. Unloading the Cabinet
11. With the cabinet supported, slowly pull the pallet away from the cabinet (see Figure 10).
Figure 10. Removing the Pallet
12. Roll the cabinet to the desired location.
44..33 EExxtteerrnnaall AACC PPoowweerr WWiirriinngg IInnssttaallllaattiioonn
You are now ready to install the Eaton 9355 UPS. Select one of the following installation options according to
your UPS configuration:
• To install the Version 1 Tie Cabinet, see paragraph 4.3.1 Version 1 Tie Cabinet Parallel Installation.
• To install the Version 2 Tie Cabinet, see paragraph 4.3.2 Version 2 Tie Cabinet Parallel Installation.
44..33..11 VVeerrssiioonn 11 TTiiee CCaabbiinneett PPaarraalllleell IInnssttaallllaattiioonn
The Eaton 9355 UPS has the following power connections:
• 3–phase (L1, L2, and L3), neutral, and ground connection for rectifier/bypass input
• 3–phase (L1, L2, and L3), neutral, and ground connection for load output
UPS System Installation