38 Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0
Figure 32. Removing Knockout Tabs
6. Route the cable(s) to the approximate location of the cover access holes.
7. Reinstall the front covers, starting with the bottom cabinet (see Figure 33).
Hang the top edge of the cover on the cabinet first, then lower the bottom edge and snap into place. Verify
that the cables fit in the access holes in the covers.
Figure 33. Reinstalling the Front Covers
8. Proceed to paragraph 4.3.4 Stabilizing the Cabinet to complete the parallel UPS installation.
NOTE After UPS startup, ensure maximum battery runtime by configuring the UPS for the
correct number of EBMs (see paragraph 6.3 Configuring the UPS for EBMs).
UPS System Installation