28 Eaton 9355 Parallel UPS (10/15 kVA) User's Guide 164201601—Rev E0
Figure 21. Version 2 Parallel Tie Cabinet Internal Cover
8. Punch holes for the conduit (AC input, UPS output, load connection, and maintenance bypass contact
wires) using a Greenlee
®
punch or similar device.
9. Verify that the parallel bypass breaker is in the OFF position (see Figure 22).
10. Mount the parallel tie cabinet to the wall and install the conduit.
UPS System Installation