7. For 160-200 kW frame: Remove
the cover panel (1) by removing
the screw and lifting the cover
panel. Remove the screws and
pull out the safety shield panel
(2) in front of the connectors.
8. For 30-50 kW frame: Locate
and remove the screws from the
relevant cable gland plates for
installing the power cables.
Eaton 93PM UPS 30–200 kVA User's and installation guide
©
Eaton Corporation plc 2017. All rights reserved. Revision: 005 Document ID: P-164000249 52 (126)