3.3 Unpacking and Unloading the UPS
If the equipment has been transported in the upright position the outside ’Tip&Tell’ indicator on the package
surface should be intact. If the arrow has turned all blue, contact the appropriate parties for reporting
inappropriate transportation.
NOTE
• TheUPScabinetisheavy.Ifunpackinginstructionsarenotcloselyfollowed,thecabinetmaytipandcause
seriousinjury.
• Donotstanddirectlyinfrontofthepalletwhileunloadingthecabinet.Ifunloadinginstructionsarenot
closelyfollowed,thecabinetmaycauseseriousinjury.
The UPS cabinet is bolted to a wooden pallet supported by wood skids. To remove the pallet, performthe
following procedure:
1. If not already accomplished, use a forklift or pallet jack to move the UPS cabinet to the installation area,
or as close as possible, before unloading from the pallet. Insert the forklift or pallet jack forks between the
supports on the bottom of the pallet (see Figure 3-4 through Figure 3-6 for the UPS cabinet centre of gravity
measurements).
NOTE
Make a visual inspection and check that there are no signs of shipping damages. The ‘Drop&Tell’ indicator on the
rearsideoftheunitshallbeintactiftheequipmenthasbeenhandledproperly.
2. Remove four bolts securing the front / rear/left /right shipping bracket to the cabinet and four bolts securing
the bracket to the pallet (see Figure 3-4). If installing the cabinet permanently, retain the shipping bracket and
securing hardware for later use.
3. Attach the ramp to the front of the pallet (see Figure 3-5):
4. If the leveling feet are not fully retracted, turn the leveling feet until they are retracted.
NOTE
Afterremovingtheshippingbrackets,theunitmustbeimmediatelymovedfromthepallet.Afterremovingthe
shippingbracketsandretractingthelevelingfeet,theunitmustnotbemovedwithajackliftwhilestillonpallet.
Note that the UPS cabinet is heavy and there are casters under the cabinet.
5. Slowly roll the cabinet toward the front of the pallet. Continue rolling the cabinet down the ramp until the
cabinet is clear of the ramp (see Figure 3-6).
6. Roll the cabinet to the final installation location.
7. If installing the cabinet permanently, retain the shipping brackets and hardware; otherwise, recycle the pal-
let, ramp, and shipping brackets in a responsible manner.