6.8. Transfer UPS from Maintenance Bypass to Double Conversion Mode
To transfer the UPS back to Double Conversion Mode:
1. The normal start position should be the following:
Output
Maintenance
bypass input
Static
bypass input
Rectier input
Bypass switch
Input switch
Output switch
Maintenance bypass switch (MBS)
Figure 6-45: Maintenance Bypass Mode
2. Turn ON the rectier switch to connect rectier input to UPS.
3. Turn ON the Static bypass switch toconnect UPS bypass input.
4. Turn ON the output switch toconnect UPS Inverter output.
5. Perform the UPS start-up procedure (bypass mode) in Section
6.3.2 Starting the UPS System in
Bypass Mode
.
6. Turn OFF the MBS, and cut o the UPS maintenance bypass (MBS) output.
7. Refer the Section
6.3.4 Transfer from Bypass to Double Conversion Mode
to Double Conversion
Mode.
The UPS is now in Double Conversion Mode
Output
Maintenance
bypass input
Static
bypass input
Rectier input
Bypass switch
Input switch
Output switch
Maintenance bypass switch (MBS)
Figure 6-46: Double Conversion Mode