Eaton 93PR 60-1200 kW UPS
Installation and Operation Manual
37
Copyright © 2021 Eaton Corporation plc. All rights reserved.
The selection of wire diameter needs to take into account the future power upgrade of UPS.
Table 3-5: Maximum Recommended Multi-core Cable Sizes (unit:mm
2
)
UPM QTY
Rectier
input
UPS
output
Bypass
input
N* Battery* PE*
4*60kW 2*150 2*150 2*150 3*150 4*150 6*150
4*62.5kW 2*150 2*150 2*150 3*150 4*150 6*150
5*60kW 2*150 2*150 2*150 3*150 4*150 6*150
6*60kW 2*150 2*150 2*150 3*150 4*150 6*150
7*60kW 3*150 3*150 3*150 5*150 5*150 8*150
8*60kW 3*150 3*150 3*150 5*150 5*150 8*150
8*62.5kW 3*150 3*150 3*150 5*150 5*150 8*150
9*60kW 3*240 3*240 3*240 5*240 4*240 6*240
10*60kW 3*240 3*240 3*240 5*240 4*240 6*240
11*60kW 4*240 4*240 4*240 6*240 6*240 8*240
12*60kW 4*240 4*240 4*240 6*240 6*240 8*240
13*60kW 5*240 5*240 5*240 8*240 8*240 8*240
14*60kW 5*240 5*240 5*240 8*240 8*240 10*240
15*60kW 5*240 5*240 5*240 8*240 8*240 10*240
16*60kW 5*240 5*240 5*240 8*240 8*240 10*240
17*60kW 6*240 6*240 6*240 9*240 8*240 10*300
18*60kW 6*300 6*300 6*300 9*300 8*300 10*300
19*60kW 6*300 6*300 6*300 9*300 8*300 10*300
20*60kW 6*300 6*300 6*300 9*300 8*300 10*300
*:The UPS busbars wiring needs to be evenly divided (see
Figure 4-9
to
Figure 4-15
for the location of the busbars).