System Operation
Copyright © 2007-2011 Eaton Corporation. All Rights Reserved.
IPN 997-00012-50H November 2011
67
Typical operation for hybrid power systems
Battery Discharge
Generator Run
Battery discharge reaches the Ah Threshold. The Generator Control output becomes active and the relay
contacts close. The Generator Run circuit is completed allowing the generator to start. Battery begins to
recharge.
Battery recharge is complete. The Generator Control output becomes inactive and the relay contacts open.
The Generator Run circuit is interrupted causing the generator to stop. Battery begins to discharge.
Configuration
To set up Generator Control:
Connect from the normally open (NO) contacts of an unused digital output relay on the
I/O board to the generator run circuit.
Ensure that no alarms are mapped to this relay.
In DCTools/Web go to Digital Outputs and configure the digital output as Active State
Energized. See Digital Outputs on page 75.
Check that Fast Charge is enabled, and check the Fast Charge configuration settings. See
Fast Charge Configuration on page 29.
Set the following parameters: