Installation Liquistation CSF48
28 Endress+Hauser
Use the ball valve 1 to set the flow rate to 1000 l/h-1500 l/h. When the sampling cycle begins,
you can use one of the relay outputs to control and open valve 2. The medium flows through the
pipe and the flow assembly into the outflow. When a settable delay time has elapsed, the
sampler takes the sample directly from the flow assembly. Valve 2 is closed again once the
sample has been taken.
The ball valve and the valve are not contained in the scope of delivery (can be ordered under
TSP No. 71180379).
5.4 Post-installation check
Make sure the suction line is securely fitted to the sampler.
Perform a visual inspection to ensure the suction line is routed correctly from the sampling
point to the sampler.
Ensure that the distribution arm is correctly engaged.
Allow the sampler to rest for a minimum of 12 hours following installation and before
switching on. Otherwise the cooling module may be damaged.
a0013458
Fig. 20: Example: Sampling from pressure piping
1 Ball valve 1
2Valve 2
3 Flow assembly

Table of Contents