Maintenance 5. Joint #2 (Replacing the Motor)
S5 Rev.5 113
Double
-check the bolts to make sure that you have not forgotten to tighten any of
them.
J
oint #2 Motor
Installation
(1)
Mount the J
oint #2 input pulley to the Joint #2 motor.
Hexagon socket head cap bolt : 1-M5×16 (with disc spring 2H-5)
Apply adhesive.
Tightening torque : 6.0 N·m (0.62 kgf·m)
Hold the
Joint #2 input pulley by using its grooves
while tightening the bolt to
prevent the
motor from turning.
(2)
Mount the motor plate to the Joint #2 motor.
Hexagon socket head cap bolt : 3-M4×16 (with disc spring 2H-4, M4 washer)
Tightening torque : 2.8 N·m (0.29 kgf·m)
(3)
Place the timing belt around the Joint #2 input pulley and mount the Joint #2 motor to
the Arm #2.
GT-SA bolt : 2-M4×16 (with M4 washer)
Tightening torque : 2.8 N·m (0.29 kgf·m)
-
Make sure the Arm #2 touches the radiat
ion sheet on the motor side surface. It is
necessary for the heat radiation of the motor.
-
Adjust the belt tension.
For details, refer to Maintenance: 5.3 Replacing the Joint #2 Timing Belt.
(4)
Attach
two cables of the Joint #2 motor (power system, signal system) to the cables
inside the manipulator
.
(
5)
Remove the backup battery from the Joint #2 motor.
(6)
Mount the Arm #2 C
over.
For details, refer to
Maintenance 3.2 Arm #2 Cover.
NOTE
NOTE
NOTE

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Epson ProSix S5 Series and is the answer not in the manual?

Epson ProSix S5 Series Specifications

General IconGeneral
BrandEpson
ModelProSix S5 Series
CategoryRobotics
LanguageEnglish

Related product manuals