❒ Replace the ash container with the ash transfer box
❒
Push the lever down to lock the ash transfer box in place
❒ Secure 2 double ball catches to the left and right of the boiler insulation using blind
rivets in the pre-drilled holes.
❒ Replace the insulated doors with the cladding (provided)
➥ Ensure that the tabs are placed correctly in the safety switch on the boiler
4.6.6 Assembling the discharge pipe and supporting post
❒ Slide the ring seal over the flange on the pipe bend (A)
❒
Using the tension ring, attach the straight pipe to the pipe bend (B)
➥ Take the tension ring apart and attach the lower part
➥ Then place the upper part of the tension ring and screw the two parts together
❒ Attach the supporting post to the straight pipe using the pipe clamp
➥ Optimum height: the pipe clamp should be fixed approx. 500 mm above the
tension ring
Assembly
4
Assembling the ash discharge system
Installation and Operating Instructions Ash discharge into a standard dustbin | M1590214_en 23