Closing and commissioning the inverter
Closing the in-
verter's connec-
tion area/hous-
ing cover, and
commissioning
NOTE!
The housing cover is fitted with a lock for safety reasons, which allows the hous-
ing cover on the inverter to be pivoted only when the DC disconnector is off.
▶
Only clip and pivot the housing cover into the inverter when the DC discon-
nector is switched off.
▶
Do not use excessive force to clip in and pivot the housing cover.
1
Place the cover on the connection
area. Tighten the five screws by rotat-
ing them 180° to the right in the indic-
ated order using a screwdriver (TX20).
2
Clip the housing cover onto the invert-
er from above.
Press on the lower part of the housing
cover and tighten the two screws 180°
to the right using a Torx screwdriver
(TX20).
Turn the DC disconnector to the "On"
switch setting. Turn on the automatic
circuit breaker.
IMPORTANT! Open the WLAN access
point with the optical sensor; refer to
the chapter headed Button functions
and LED status indicator on page 26
Starting the in-
verter for the
first time
When starting the inverter for the first time, various setup settings must be con-
figured.
If the setup is canceled before completion, the input data is not saved and the
start screen with the installation wizard is shown once again. The data is saved in
the event of an interruption, e.g., a power failure. Commissioning is continued at
the point at which the interruption occurred after the power supply is restored. If
the setup was interrupted, the inverter feeds energy into the grid at maximum
500 W and the operating status LED flashes yellow.
The country setup can only be set when starting the inverter for the first time. If
the country setup needs to be changed at a later date, contact your installer/
technical support.
67