Chapter 3: Installation
Installing the Intermediate Well Flange
1. Place the intermediate well flange (82) onto the intermediate well.
2. Install self-drilling screws (83) to secure the intermediate well flange (82) to the bin floor.
Figure 3-19 Installing the intermediate well flange
82
Intermediate well flange
83
Self-drilling screws
After You Finish
Repeat the above procedure to install the intermediate well flange in all the remaining intermediate wells.
30
PNEG-2308 Chain Loop Power Sweep