Setpoint Programmers
Setpoint programmer – Pre Plot Display
Revision 9 900 Control Station User Guide 123
May 2014
Auxiliary PV Engineering Units
Current PV2 value
Current PV3 value
Primary button to select Primary PV graph
Auxiliary button to select Auxiliary PV graph
Setpoint Programmer current Status
Set Point indicator to indicate color of Setpoint plot
Process Variable indicator to indicate color of Process Variable plot
Operate Display button to navigate to associated Setpoint Programmer Operate Display
As shown below a second pre-plot indicates the profile of the SPP Auxiliary Setpoint output profile
(soaks only). The SPP Process Variable # 4 input (PV4) is plotted against the Auxiliary Setpoint
output pre-plot graph.
Setpoint Programmer Pre-Plot Graph attributes
1. The content of the pre-plot graph is determined by reading the profile content of the Setpoint
Programmer function block. Time is presented on the X axis and the SP value is presented on the Y
axis of the graph.
2. The amount of time contained within the pre-plot graph is determined by:
a) The number of user programmed segments in the profile (The user may use from 2 to 50 of the
available segments for his program.)
b) The time units specified for the profile (minutes or hours)