3 Preparations for Power-On
Commissioning
3.1 Tools
The following table lists the tools required for power-on commissioning.
Table 3-1 Tools
Tools
Phillips screwdriver Flat-head screwdriver Utility knife
Multimeter Electroprobe Network cable tester
Cable tie Insulation tape Marker
FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario) 3 Preparations for Power-On Commissioning
Issue 02 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd. 26