5.2 Fire Extinguishing System Commissioning (3C)
Prerequisites
The
re alarm control panel has been powered on.
The management system is working properly.
D ANGER
Before commissioning the re extinguishing system, disconnect all control
cables to the electromagnetic valve of the
re extinguisher cylinder to avoid
extinguishant release and damage to equipment due to misoperations during
the commissioning. After the commissioning is completed, reconnect cables to
the electromagnetic valve.
Do not remove the safety pin before the
re extinguishing system is
commissioned; otherwise, extinguishant may be released by mistake.
To avoid damaging the detector probe, keep a proper distance between the
heating device and the heat detector.
Preparations
Tools: multimeter, smoke pistol, heating device, Phillips screwdriver, at-head
screwdriver
Documents: re extinguishing system conceptual diagram (standard), re
extinguishing device layout diagram (standard)
Skill requirement: re engineer
NO TE
For the diagrams, see the initial conguration parameter manual for the solution in use.
Procedure
Step 1 Press and hold the ON/OFF key on the encoder for 1 second to start the encoder.
Step 2 Press # to switch the mode. When 324 is displayed on the screen, use a dedicated
external connection cable to connect the terminal device and set the address code
for the device on the bus.
FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario) 5 System Commissioning
Issue 02 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd. 66