Figure 4-2 Clear Faults
Step 3 View active alarms and ensure that the Battery cabinet shutdown alarm has
disappeared from the alarm list.
----End
4.3 Commissioning Smart Cooling Products
Prerequisites
The power-on commissioning for the upstream PDF of air cooled precision smart
cooling products is completed.
● Smart cooling products that use power crossfeed can be powered on only after
both power inputs are connected.
● Teamwork settings can be performed only after all smart cooling products in a
group have been powered on.
Preparations
Tools: none
Documents: power supply and distribution drawings and parameters, NetCol5000-
A(025, 035) in-row air cooled smart cooling product user manual (300 mm width)
Skill requirement: cooling engineer
Procedure
Step 1 Switch on the input power circuit breakers for the air cooled precision smart
cooling product indoor units in the upstream PDF, and switch on fan circuit