EasyManua.ls Logo

Huawei FusionDC1000A - Powering on and Starting the UPS; Power-On

Huawei FusionDC1000A
85 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
distribution drawings and parameters. After the AC input starts properly, the ATS
controller starts.
NO TE
A password is required to log in to the congurations page. Set the password by using
the Up, Down, and Enter buttons. The initial password is 0001.
Language setting: Default screen > Main Menu > Device
Conguration > Language.
On the default screen, hold down . The main menu screen is displayed.
On the main menu screen, select system conguration and press .
On the main menu screen, select device
conguration and press . On
the device conguration screen, you can set thresholds for parameters.
Step 8 Set the ATS controller to auto mode.
----End
4.1.2 Powering On and Starting the UPS
4.1.2.1 Power-On
Prerequisites
The SPD circuit breaker is ON.
Before powering on the UPS, measure the voltage and frequency of the upstream
power distribution switch of the UPS cabinet. Ensure that the phase voltage is
within the range of 80–280 V AC and the frequency is within the range of 40–70
Hz.
Procedure
Step 1 Switch on the MCCB (skip this step in the case of ATS input).
Step 2 Switch on the UPS input circuit breaker QF1.
The UPS is powered by the mains and initialization begins. The LCD displays an
initialization progress bar.
----End
FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario) 4 Commissioning Core Devices
Issue 02 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd. 35

Table of Contents

Other manuals for Huawei FusionDC1000A

Related product manuals