Step 5 Turn on the upstream switch for the emergency light power cable.
The emergency light turns o, and the power indicator turns on.
Step 6 Press the red button of the emergency light. The emergency light turns on. When
you release the red button, the emergency light turns
o.
Figure 4-7 Red button of the emergency light
(1) Red button of the emergency light
● The red button is located at one side of the emergency light.
● If the result expected for each step appears, the emergency light is working properly.
----End
4.6.2 (Optional) Commissioning the ASD
Preparations
Tool: smoke pistol
Documents: drawings and parameters for power supply and distribution as well as
re extinguishing, documents delivered with the ASD
Skill requirement: re engineer
Procedure
Step 1 Switch on the input power circuit breaker for the ASD power box for the protected
area and connect the ASD battery based on the power supply and distribution
system diagram.
Step 2 (Optional) Perform power-on commissioning by following instructions in
documents delivered with the ASD.
The ASD is commissioned before delivery. The ASD that is used as a replacement must be
commissioned as instructed by the delivered documents.
FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario) 4 Commissioning Core Devices
Issue 02 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd. 49