Step 2 Remove the server node.
For details, see 8.3.3 Removing an XH321 V5.
Step 3 Place the server node on the ESD workstation.
Step 4 Take the component out of its ESD bag.
Step 5 Determine the position of the supercapacitor.
Step 6 Vertically insert the supercapacitor into the holder until the supercapacitor is
locked.
Figure 8-22 Installing a supercapacitor
Step 7 Connect the cable between the supercapacitor and the screw-in RAID controller
card.
Step 8 Install the supercapacitor and its holder.
1. Install the supercapacitor holder into the node panel and tighten the screws
to secure the supercapacitor holder. See (1) in Figure 8-23.
2. Install the node panel. See (2) in Figure 8-23.
3. Tighten the screws to secure the panel. See (3) in Figure 8-23.
Figure 8-23 Installing a supercapacitor holder
FusionServer Pro XH321 V5 Server Node
Maintenance and Service Guide 8 Parts Replacement
Issue 17 (2021-03-09) Copyright © Huawei Technologies Co., Ltd. 60