When hoisting the ESS, ensure that the four corner ttings of the ESS are aligned
with the marked mounting positions for corner ttings on the concrete platforms.
Prepare and install the lifting eyes and steel ropes.
Figure 4-3 Hoisting the ESS
Step 2 Cut open the protective cover using a utility knife and remove the protective cover.
● When removing the protective cover, take protective measures for working at
heights.
● Do not remove the protective cover in bad weather conditions such as rain and
snow.
The protective covers are added to protect the ESS during transportation.
Step 3 Secure the ESS using four angle steels.
LUNA2000-2.0MWH-1H0, 2H0 Smart String ESS
User Manual 4 Installation