5.3.3 Installing the PDC on an ESD Floor
Context
A support is required when the PDC is installed on an ESD oor. The support
height depends on the height between the ground and the ESD oor.
Procedure
Step 1 Lower the leveling feet of the PDC using an adjustable wrench until all castors are
o the ground and the cabinet is level.
Step 2 Lift the PDC onto the support and align the mounting holes in the PDC with those
in the support.
Step 3 Level the PDC by adjusting the leveling feet.
Figure 5-10 Leveling PDC
(1) Leveling foot (2) Level
 
Step 4 Insert four M12 bolts into the mounting holes in the PDC and support, and
partially tighten the bolts.
● Scenario 1
Figure 5-11 Securing the cabinet
● Scenario 2
(Optional) When the PDC installation environment is 5# channel steel and that the PDC
cannot be secured using the mounting holes, secure the PDC using the mechanical part
shown in the following gure.
PDU8000 Modular Precision PDC V2.0
User Manual 5 Installation Guide