Table 6-3 Cable installation checklist
No. Check Item Result
1 All bolts are tightened, especially the bolts used for
electrical connection. Flat washers and spring
washers are installed properly.
□Yes □No
2 Cable installation meets the cable routing
requirements.
□Yes □No
3 Cables are routed in the way convenient for future
maintenance and expansion.
□Yes □No
4 There are no unnecessary adhesive tape or cable
ties on the cables.
□Yes □No
5 Exposed parts near the wiring terminals and lugs
are wrapped in PVC insulation tape or heat
shrinking tubing.
□Yes □No
6 The cable routing for power cables and monitoring
cables meets the requirements for routing power
cables and signal cables and complies with the
cable routing plan.
□Yes □No
 
6.2 Power-On Commissioning
Context
● The power-on commissioning process requires at least two qualied
electricians, one responsible for operations and the other for monitoring.
● Cautions and warnings must be properly placed onsite.
● Users are categorized as admin and operator. Admin users have more rights
than operator users.
● Powering 
o the PDC disconnects the power supply to the downstream devices.
Exercise caution with this operation when the PDC is supplying power to a
working system.
Procedure
Step 1 Check cable connections and the mechanical performance.
1. Check that cables are connected correctly outside the cabinet. Check that all
bolts are secured for inlet and outlet cables and tighten a bolt if it is loose.
2. Check that ground cables are properly connected.
PDU8000 Modular Precision PDC V2.0
User Manual 6 Commissioning Guide