INSTALLER SETTING
ENGLISH
Leaving Water target temperature °C
Pre heating
Step
Heating ready for tiling
Holding time
76
INSTALLER SETTING
Screed drying
This function is a unique feature of AWHP that, when AWHP is installed in a new concrete
structure, controls the specific temperature floor heating out temperature for a certain period of
time to cure the floor cement.
• In the installer setting list, select Screed drying category, and press [OK] button to move to the
detail screen.
How to display
Main Screen - Displays 'Screed drying' on the desired temperature display. The step in progress
at the bottom of the display is displayed.
Setting value
- Start-up step: 1~11
- Maximum temperature : 35 °C~55 °C
- Step 8 Holding time : 1 days~30 days
Function operation
- It is performed by the following procedure from the selected starting step.
- After all steps are completed, turn off the cement curing operation.
※ If the upper limit setting value of the heating LW temperature is 55 °C or lower, it is set to
55 °C forcibly.
If the lower limit setting value of the heating LW temperature is 25 °C or higher, it is set to
25 °C forcibly.
Step 1 2 3 4 5 6 7 8 9 10 11
Leaving Water
target
temperature[°C]
25 Max.T Off 25 35 45 Max.T Max.T 45 35 25
Duration
[hours]
72 96 72 24 24 24 24
Holding
time
72 72 72
OK
NOTE
• During Screed drying operation, button input except for installer function and temperature
display is restricted.
• When the power is applied again after a power outage during product operation, the
product operation state before power failure is remembered and the product is
automatically operated.
• Screed drying operation stops when an error occurs / When error is cleared, restart
cement Screed drying. (However, if the wired remote control is reset to the error
occurrence state, it is compensated in the unit of one day)
• Upon releasing after an error, Screed drying operation may take up to 1 minute of waiting
time after boot up. (The Screed drying operation status is judged as 1 minute cycle.)
• During Screed drying operation, installer function Screed drying operation is selectable.
• During Screed drying operation, starting operation, low noise mode off, low noise time
setting off, hot water off, solar heat off.
• During Screed drying operation, simple, sleep, on, off, weekly, holiday, heater does not
execute reservation operation.