Auxiliary single-sheave boom top
5.1 Installation / removal
5 - 2 3 112 441 en Lattice extension operating instructions
GMK 4100/4100-L/5095
11.01.2008
Removing
Sling the auxiliary single-sheave boom top;
à p. 2 - 10.
(A) – In transport position
Pull out the pins (1) and (2).
(B) – In working position
Pull out the pins (1), (2) and (3).
Raise the auxiliary single-sheave boom top
from the main boom head.
Insert the pins (1) and (2) in the bearing
points.
Insert the thin pin (3) in the bearing point.
Secure all pins with linchpins.