Pre-Installation Inspection:
Correct model     Correct capacity
Correct platform size    Correct options
Correct manuals & decals
Structural Inspection:
Liftgate is centered on vehicle rear door &
       mounted per dimensions in this manual.
Pump box is mounted securely.
All installation welds are done per instructions
       in this manual.
All roll pins, bolts & fasteners on liftgate 
       are tight.
All hardware & fasteners, used to secure
       liftgate to vehicle body, are tight.
Ensure platform ramp touches ground when 
       runner is 1” above ground. The main platform 
       & fl ipover surfaces should be level to one 
       another and rest evenly when touching the 
       ground.
Verify runner slide pads are in adjustment per
 STEP 18 in this manual.
Hydraulic Inspection:
Fluid is at correct level (See OPTIMIZE HY
       DRAULIC FLUID LEVEL step in this manual.)
No leaks from hydraulic fi ttings in pump box
No leaks from hydraulic line connections
Electrical Inspection:
Power/charge plug and terminals are clean & 
       tight.
Individual wire connections are tight.
Circuit breaker (150A) is installed in battery box
       (if equipped) or by truck/tractor battery.
Batteries are fully charged, all cable 
       connections are tight & tiedowns are tight.
Solenoid wiring connections are tight.
Wiring harness connections are tight.
Electrical cable connections are tight & 
       secured clear of moving parts & sharp edges.
Model:______________________ Date: ____________________
Serial Number: _______________  Technician: _______________
Operation Inspection:
Liftgate operates correctly using all main & 
       optional control switches.
All BMR: Platform unfolds in 5 to 7 sec. 
All BMR: Platform can be lowered onto the 
       bottom stop position for dock loading, and 1” 
       below the threshhold plate.
All BMR: platform folds in 5 to 7 sec.
  BMR-35 or -44 only
Unloaded platform lowers in 8 to 20 sec.
Unloaded platform raises in 9 to 21 sec.
  BMR-55 or -66 only 
Unloaded platform lowers in 12 to 23 sec.
Unloaded platform raises in 13 to 26 sec.
All BMR: Unloaded platform raises and lowers 
       evenly in GD and PD modes. Maximum 1” 
       difference of runners from side to side.
All BMR: Platform stores securely behind both
       column wedges.
Cycle counter indicates total number of up and
       down cycles and adds 1 more count each time
       platform is raised and lowered.
Decals in correct location and legible.
Verify all lights are operational
Platform lights turn ON when platform is un-
       folded, and turn OFF when platform is stowed.
Taillights, stop lights, turn lights, and backup
       lights turn ON and OFF correctly.
NOTE: The following times are for 56” bed 
height, aluminum platform and 
fl ipover, 85” W x 42” + 42” L, Exxon 
Univis HVI-13 oil, & temperature at 
70°F. Times are for reference only 
and may vary for larger platforms, 
smaller platforms, steel platforms, or 
temperature changes.
PRE-DELIVERY INSPECTION FORM
Important! This pre-delivery checklist is to aid the installer in confi rming the proper installation of 
this Maxon product.  It is not a comprehensive list and does not replace the use of the installation 
manual. The installer is responsible for following all instructions in the installation manual.