SECTION 2.0 - INSTALLATION
2.1 Crate Removal
CAUTION: Equipment used to move or lift the milk cooler must be rated for the weight of the
milk cooler. Approximate weights are provided in Section 8.
1. Remove any open-type crating and the packaged parts. Do not remove the skids attached to the
milk cooler legs at this time.
2. Inspect the milk cooler and report any damage to the transportation carrier. File a claim
immediately if the milk cooler is damaged.
3. Move the milk cooler into the milk house and position it to meet all regulatory requirements for
the locality.
4. Once in place, the skids can be removed.
2.2 Skid Removal
1. Raise one end of the milk cooler with the floor jack placed beneath the skid’s cross brace. Securely
block the skid to ensure safety and stability while removing the self-tapping screws from the
bottom of each leg.
2. Lower the milk cooler and repeat the procedure on the opposite end.
3. Remove cross-bracing members, leaving the two skids under the milk cooler’s legs.
4. Raise one end of the milk cooler with a floor jack and wooden-cradle block. Pivot the skids away
from the milk cooler. Lower the milk cooler and repeat the procedure for the other end.
Figure 2 - Skid Removal
!
Sentry II with Auto-Dosing Assembly Operating Instructions 3 Effective April 1, 2000

Table of Contents

Other manuals for Mueller SENTRY II

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Mueller SENTRY II and is the answer not in the manual?

Mueller SENTRY II Specifications

General IconGeneral
BrandMueller
ModelSENTRY II
CategoryController
LanguageEnglish

Related product manuals