INTELLIGENT PDU USER MANUAL
Administrator Privileges.
1. Select the Control & Manage folder from the Home icon.
2. In the Power Control panel, select the outlet that must be switched on, switched
off, or reboot.
3. Select the desired Power Control from the dropdown menu.
4. Select Apply.
Setting the Outlet Power On/Off Delay for Panduit PDUs
This is only applicable to outlet-switched PDUs. When the PDU is turned ON, outlets
will consecutively power on from Outlet 1 to the highest available outlet number.
1. Select the Home Icon then Control & Manage from the drop-down menu in the
Web UI.
2. Select the outlet(s) for which to set a delay by clicking on the pencil icon.
3. Configure the length of the delay and/or length of reboot.
4. Select Save.
Outlet Power Sequence Setup
The outlets can be programmed to have a pre-determined on delay or off delay. (E.g.
On Delay can be used to implement power on sequencing to avoid surge spikes or
circuit breaker overload associated with IT equipment all being turned on at the same
time.)
Figure 20: Control & Manage PDU