4.2 Transport and storage of the machine 17
4.2 Transport and storage of the machine
The cleaning machine can be loaded onto a truck trailer with a front stacker after the correspond-
ing disassembly of the machine segments.
When transporting or storing, the machine must be secured against inadvertent slipping with suit-
able attachment means.
Observe the following items for setting up and commissioning:
This machine must only be loaded with suitable lifting gear (e.g. front stacker).
The required carrying capability of the means of transport is according to this machine's
dead weight and unloading of the machine segments (see Technical data, page 16).
Ensure a secure, load-bearing and stable underground.
4.3 Machine setup and commissioning
When setting up, observe the infeed direction of the cleaning machine.
Set up the cleaning machine horizontally.
Put a roller table in front of the machine and a roller table behind the machine.
Align the roller tables with a yardstick levelly and laterally along the guide rollers of the
cleaning machine.
Now fasten the cleaning machine and roller tables to the floor
Install the extraction unit properly.
Create the power supply to the machine (phase sequence L1-L2-L3 right rotating field).
Check all emergency off buttons for triggering.
Safety doors must be closed.
Switch on the machine by putting the main switch in the On position
Operate the emergency off reset through the button.
The deduster is started automatically.
Start the machine by pushing the respective start buttons. (see page 21)
Check the rotating direction of the cleaning machine and reverse polarity of the connec-
tion if required.
Check all emergency off devices for function
The place of setup of the machine must be selected to
warrant proper stance on firm underground. When setting
up the machine, observe the correct safety distances.
Observe the respective operating instructions for any fur-
ther setting measures.
Attention: The machine is designed for a right-ward turn-
ing rotating field.
! Connection polarity of the supply must only be reversed
by an electrician!