Commissioning Checklist
Controller Mounted on suitable flat heatsink with appropriate heatsink compound ?
Power wiring checked, shortest routes taken where possible ?
Light wiring checked, use calibrator to verify controller correct switch operation.
Accelerators set-up and checked 0 – 100% ?
Personalities all set, checked and record filled out ?