This section provides an operational overview of the real-time functional tasks of the Maxum
II.
Startup Tasks
Applying Power
Valid Database
Oven Temperature
Cycle Control Flag
Timed Event Scheduling
Time-Of-Day Clock
Schedule of Events • Frequency Events
Analysis Cycle Clock
Accessing System Controller
Analysis Cycle Clock
SYSCON Cycle Clock
Valve Events
Manual Operations via User Interface
Startup Tasks
On start-up, when primary AC power is applied to the analyzer, the analyzer first processes
whatever electronic self-tests and diagnostics are required such as PROM, RAM, A/D, and
communication ports. This processing occurs within 5 seconds.
System-related initial messages are generated and output to the network ports. Appropriate
initial messages are then displayed on the Maintenance Panel and completed within 20 to 25
seconds. If the analyzer cycle clock is in RUN or CAL mode, an appropriate alarm may be
generated during this internal test and the following startup period.
System Functions
3.2 Functions
Maxum edition II Analyzer General Maintenance
10 Manual, August 2018, A5E42019842001

Table of Contents

Other manuals for Siemens Maxum II

Related product manuals