Commissioning
5.6 Commissioning with STARTER
SINAMICS G110D
72 Operating Instructions, 07/2016, FW V3.63, A5E36768472B AB
Image 5-7 Select power unit dialog
Using the order number of the Inverter, select the appropriate Inverter power unit.
Press "next" to display the summary screen.
Image 5-8 Summary dialog
The summary screen displays the configuration settings that have been completed up to this
point of the process. The details of the configuration can be copied to the clipboard and