71
SJ6826 RT, SJ6832 RT
221587ABA
Move the MEWP through a doorway Section 6 – Additional Procedures
16. Put the locking pin in the right extension to lock
the right-side extension guardrail and the front
guardrail in position.
17. Swing the front side guardrail forward.
18. Put in the locking pin to lock the front side
guardrail in position.
19. Attach the platform control console and
outrigger controls (optional equipment) to the
front right of the platform. Lock them in position.
WARNING
Before you operate this MEWP, make sure that
the guardrail system does not have loose or
missing lock-pins. The guardrail system must be
in the vertical position. Lock all pins correctly. An
incorrectly locked guardrail can cause a fall, which
can result in death or serious injury.
6.7 Move the MEWP through a
doorway
WARNING
Only do this procedure on level ground. If you do
not obey, there is a risk of death or serious injury.
1. Make sure the height/width of the doorway is
sufficient to let the MEWP drive through.
2. Before you operate the MEWP, do a full
inspection of the site (refer to section 2.4).
Identify hazards in your work area.
3. Make sure the platform is fully lowered.
4. Disconnect and remove the platform control
console. (refer to section 6.5-1)
5. Fold the guardrails if it is necessary. Refer to
section 6.6 for the procedure on how to fold the
guardrails.
WARNING
Crush hazard. Make sure that there are no
personnel in the path you will travel. Tell personnel
around the path before you move the MEWP. Use
a second person to monitor the movement of
the MEWP. Make sure that person stays at a safe
distance. If you do not obey, there is a risk of death
or serious injury.
6. Connect the platform control console cable to
the electrical plug in the engine compartment
of the MEWP. Refer to section 6.5.