TECDrive20-EU Series Inverter Product overview
-7-
2.1.5 Basic commissioning
Complete the basic commissioning as follows before using the inverter.
1. Perform autotuning if required. Remove the motor load, if possible, to perform dynamic
parameter autotuning; and if the load cannot be removed, you can perform static
autotuning.
2. Adjust the ACC/DEC time according to the actual operation conditions of the load.
3. Perform commissioning on the machine in jogging mode and check whether the
rotating direction of the motor meets the requirement. If no, exchange the wires of any
two phases of the motor to change the running direction of the motor.
4. Set all control parameters and then run the machine.
2.2 Data related to safety standards
IEC/EN 61508 (type A system)
* PTI: proof test interval.
** According to the categorization defined in EN ISO 13849-1.
2.3 Decommissioning
Before decommissioning any safety system from active service:
Evaluate the impact of decommissioning on adjacent operating units and facilities or other
field services.
Conduct a proper review and obtain required authorization.
Ensure that the safety functions remain appropriate during decommissioning activities.
Implement appropriate change management procedures for all decommissioning activities.
2.4 Product specification
AC 1PH 200V–240V, rated voltage: 230V
AC 3PH 200V–240V, rated voltage: 230V
AC 3PH 380V–480V, rated voltage: 400V
Allowable voltage
fluctuation
Refer to section 2.7 "Rated specifications".
50Hz or 60Hz; allowed range: 47–63Hz