6 Commissioning
41
26
Press the [Connect] key on all data loggers and Saveris routers one
after the other to synchronize the components.
27
Close the dialogue with [OK].
The hardware is now ready for operation.
For how to mount the hardware on the wall for example, see section
6.10.3 Wall mounting of data loggers
.
6.9 Configuring hardware
Use the installation instructions for the initial commissioning of the system.
The following requirements must be fulfilled for the rest of the hardware
commissioning process:
The Saveris base is ready for operation.
All data loggers are registered on the Saveris base.
The Saveris software is installed.
A project has already been created.
Measurement operation has been ended.
1
Connect the Saveris base via the USB or network cable to a computer
on which the Saveris Client is installed.
For continuous operation of the system, connection of the Saveris base
to the computer via an Ethernet cable is recommended.
The startup wizard is launched.
2
Click on [Next >].

Table of Contents

Other manuals for TESTO Saveris T3

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the TESTO Saveris T3 and is the answer not in the manual?

TESTO Saveris T3 Specifications

General IconGeneral
BrandTESTO
ModelSaveris T3
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals