7.2  Maintenance procedures 
Two preventive maintenance procedures are defined for this valve. These are: 
 
• 
Replacement of isolation seals (gate and body seal of sealing ring) and valve cleaning. Refer to 
chapter: «Replacement of isolation seals and cleaning». 
• 
Replacement of actuator and actuator shaft seals. Refer to chapter: «Replacement of actuator and 
actuator shaft seals». 
 
 
 
 
Required frequency of cleaning and replacement of seals is depending on process 
conditions. 
• 
A critical factor influencing the maintenance period is the lifetime of the vacuum 
grease, being limited under increased temperature. In this case grease will 
separate to PTFE and oil. The oil may flow and contaminate the valve parts. 
VAT can give the following recommendations for preventive maintenance: 
 
Replacement of  unheated 
1)
 
heated ≤
≤≤
≤ 80 °C 
1)
 
heated > 80 °C 
1)
 
 (gate and 
body seal of sealing ring) 
200’000 cycles  6 months but 
max. 200’000 cycles 
3 months but 
max. 200’000 cycles 
 
 
 
 
NOTICE 
Vacuum grease 
Vacuum grease may be distributed and contaminate the valve. 
Prevent gap between body and sealing ring from air gun cleaning. Do not clean the 
gap between body and sealing ring with compressed air. 
 
See figure below: 
 
 
 
 
Body 
 
 
 
Gap 
 
Sealing ring