www.bodor.com/service@bodor
.com
8
th
week before the arrival
of the equipment
1) Appoint a person in charge of transfer and
preparation of the machine tool.
2) Assign operating personnel, maintenance
personnel and programming personnel.
3) Agree on the training period of
professionals.
4
th
week before the arrival
of the equipment
1) Install the electrical interface at the
installation site.
2) Prepare standard wiring and circuit
protection according to the regulations.
4
th
week before the arrival
of the equipment
Air compressor (only when
prepared by the customer)
Install the compressed air feeder at the
installation site.
2
nd
week before the arrival
of the equipment
1) Nitrogen,
2) Oxygen
3) Cooling water
4) Compressed air (optional)
1.1 Installation Conditions
Requirements for ground
1) The ground of equipment installation should be flat, the flatness be within ±5mm, and the concrete thickness of the entire
installation surface be not less than 200mm.
Requirements for space
2) The distance between left side and rear side of the machine tool and the workshop wall should be more than 1,200mm;
the distance from the laser to the wall should be more than 1,000mm.
3) In order to prevent the occurrence of a fire, the processing site should be equipped with appropriate fire extinguishers,
and fire-fighting access should be set aside.
4) The detailed technical indicators are subject to the Foundation Map attached with our company.