The preparedness plan provides the preparedness scheme required by the customer before the arrival of the equipment.
See relevant chapters of the guide of complete machine assembly and disassembly for details. The time planning is for
reference only, and the details are subject to the actual order.
Before the arrival of the
equipment
10
th
week before the arrival
of the equipment
1) Determine the installation site of the
machine tool, and at the same time consider
the site requirements according to the site
layout drawing.
2) Check ground conditions:
•Ground quality
•Flatness
•Gap
3) Pay attention to machine weight and size.
4) Check climatic conditions:
•Room temperature.
•External air purity.
5) Check transport routes:
•Doorway size
•Height of breast beam
•Height of cable rack
•Switchyard around the corner, etc.