4. Attach the hoisting hooks and cables to the steel rings on the inverter.
5. Attach the crane hook to the steel ring on the hoisting cables.
6. Lift up the inverter and transfer to the installation site steadily.
7. Remove the hoisting cables.
Figure 3-11 : Attaching the Hoisting Cables
Steel Ring
Crane Hook
Hoisting Hook
23
Transportation & Installation Preparation