The drain directs solvent spills from the bottle area on top of the ASE 150 to
the rear panel. A drain hose connects to the fitting. For installation
instructions, see Section B.2.2
.
2.3 ASE 150 Extraction Process
Preparing to Run an Extraction
The following steps are required before the ASE 150 can perform an extraction.
Refer to Chapter 3
for detailed instructions for each step.
Fill the solvent reservoir.
Prepare the sample and load it into the sample cell.
Install the waste bottle and collection vessel.
Select or create a method.
Press the START button.
Verify that the STATUS on the STATUS screen is OVEN READY (see Figure 2-5)
and the LED on the
START button is flashing.
Install the sample cell in the cell holder and close the cell door.
Press the START button.